Antecedents of Smart Contract Adoption in Public–Private Partnership Construction Projects: A Systematic Review and Competency-Extended TOE–Institutional Framework

  • Francis Nuako
  • , Stephen Akunyumu
  • , Kofi Owusu Adjei
  • , Frank Ghansah
  • , Francis Bondinuba

Research output: Contribution to journal › Article › peer-review

2 Downloads (Pure)

Abstract

This study systematically reviews the antecedents of smart contract adoption in public–private partnership (PPP) construction projects and develops an integrated competency-extended Technology–Organisation–Environment (TOE)–Institutional framework. It synthesises evidence on technological, organisational, environmental and institutional conditions influencing adoption while examining stakeholder competencies required to translate favourable adoption conditions into implementation. The study further distinguishes adoption intention from actual implementation and expected PPP outcomes, providing a theoretically grounded framework for understanding smart contract adoption in complex PPP environments.
A systematic literature review was undertaken using PRISMA-informed procedures. The review identified 89 records, of which 46 provided sufficient evidence for classification. 26 full-text Tier 1 studies formed the principal evidence base for quality appraisal and thematic synthesis, while 17 abstract-level Tier 2 studies supported descriptive mapping and three recent studies provided supplementary evidence. Deductive coding mapped adoption factors to TOE and Institutional Theory, while inductive coding identified stakeholder competencies, barriers, applications and expected outcomes. The synthesis was subsequently used to develop the proposed competency-extended TOE–Institutional framework.
The review identifies technological, organisational, environmental and institutional conditions as interrelated antecedents of smart contract adoption intention in PPP construction projects. Stakeholder competency emerges as a distinct implementation-enabling capability rather than simply an organisational resource. Key constraints include regulatory uncertainty, interoperability limitations, cybersecurity concerns, implementation costs and skills shortages. The evidence also indicates that adoption intention should be distinguished from actual implementation and expected outcomes. Accordingly, the study proposes a competency-extended TOE–Institutional framework linking adoption antecedents, stakeholder competency, adoption intention, implementation and expected PPP outcomes while recognising barriers as constraining conditions.
The review is limited by the relatively small full-text evidence base (26 Tier 1 studies), methodological heterogeneity and the use of 17 abstract-level studies only for descriptive mapping. The surviving audit trail also limits complete reconstruction of database-specific search details. Furthermore, no Ghana-specific Tier 1 study was identified, restricting direct contextual generalisation. The proposed framework should therefore be regarded as evidence-informed rather than empirically validated. Future research should test its constructs and relationships across PPP contexts, particularly in developing economies, and examine how stakeholder competency influences the transition from adoption intention to actual implementation.
The findings provide a practical roadmap for PPP authorities, construction organisations and technology providers considering smart contract adoption. Organisations should begin with controlled pilot applications in progress verification, payment certification and document tracking while strengthening stakeholder competencies through interdisciplinary training. Public agencies should clarify legal status, liability, cybersecurity, data ownership and dispute-resolution requirements. Industry stakeholders should develop interoperability standards and integrate smart contracts with BIM and existing digital systems. In emerging economies such as Ghana, phased implementation is recommended to test technical, institutional and competency readiness before broader deployment.
Responsible smart contract adoption in PPP construction projects could strengthen transparency, accountability and trust in infrastructure delivery by improving transaction traceability, contractual compliance and payment administration. Greater automation and verifiability may also reduce opportunities for manipulation, payment disputes and information asymmetry among public and private stakeholders. However, these benefits depend on appropriate governance, stakeholder competency, cybersecurity safeguards and inclusive capacity development. The proposed framework therefore supports socially responsible digital transformation by emphasising institutional legitimacy and human capability alongside technological readiness, particularly in emerging economies where transparent and accountable infrastructure delivery remains important.
The study advances smart contract adoption research by moving beyond the simple integration of TOE and Institutional Theory, which has already appeared in prior studies. Its originality lies in theoretically distinguishing **stakeholder competency from organisational readiness** and positioning competency as an implementation-enabling capability. Supported by Human Capital Theory, the proposed framework separates antecedent conditions, adoption intention, actual implementation and expected PPP outcomes while recognising barriers as constraining conditions. This provides a more explicit explanation of why favourable technological, organisational and institutional conditions may generate adoption intention without necessarily resulting in successful smart contract implementation.