Abstract
This PhD thesis summarises an investigation of heat recovery from industrial processes. Cable tunnels and data centres are the waste heat sources studied. The work presented here determines the potential, evaluates the feasibility and benefits, and challenges the barriers currently preventing the owners and operators of these assets, from capturing and reusing the heat generated. The results of this research study were obtained through extensive analysis of data from published information, site visits and engagement with the industry through a survey. Barriers and enablers to adoption of heat recovery were identified through interviews with industry representatives and independent consultants. Case study spreadsheet modelling was used to assess the feasibility of a range of heat reuse scenarios. Spreadsheet Model 2 for the cable tunnel analysis and the data centre energy model were developed as part of this PhD, while the published heat recovery calculations and finite-element temperature outputs reported by Revesz et al. (2019) and Davies et al. (2019b) were adopted as inputs to the cable tunnel analysis. Cable tunnels are specialised underground infrastructure which are present in most major cities. They enable the transmission of electrical energy using high and medium voltage power cables between power sources and points of use. The busy urban environment necessitates the construction of cable tunnels to avoid the use of pylons and overhead lines. In London alone, there are plans to operate nearly 100 km of cable tunnels by 2026. Housing of electrical cables in tunnels enables them to be operated more safely and provides easier access for maintenance. However, as there are in many cases significant quantities of heat generated due to transmission losses, hence the tunnels require cooling and provide an opportunity for heat recovery.
Data centres are typically purpose-built or converted buildings, dedicated to the housing of computer servers, storage and networking equipment, which are responsible for day-to-day support of global computing needs. Data centres require careful design and management to ensure minimal downtime, security, and efficiency. While operating, large quantities of heat are generated by the IT equipment and need to be removed. According to published information, nearly 12,000 data centres are located in the United Kingdom alone. In addition, a substantial proportion of them are located in cities, close to potential heat users. Both of the above industrial processes i.e. cable tunnels and data centres operate continuously (24 hours a day) throughout the year, and a consequence of their normal operation is the conversion of electrical energy to low-temperature heat, which is typically rejected to the atmosphere. This thesis presents the results of a research study that investigated the potential for recovery of waste heat from cable tunnels and data centres. It quantified and analysed the benefits, including reductions in carbon emissions and operational costs, and identified technical, economic and institutional barriers currently preventing heat recovery from these sources in the United Kingdom. For the cable tunnel case study, the analysis indicated potential annual savings of approximately 4,000 kWh of combined heat and electrical energy, 570 kilograms of CO₂e and £127 per metre of tunnel. Extrapolated across London’s existing 62.7 km cable tunnel network, this corresponded to potential annual savings of approximately 250.8 GWh of energy, 35,739 tonnes of CO₂e and £7.97 million. For the data centre case study, the best-performing heat recovery configuration, combining direct-to-chip liquid cooling with recovery from the data centre air and connection to a 4G heat network, reduced energy input and operational carbon emissions by approximately 86%, and operating costs by approximately 66%, relative to the gas boiler counterfactual. Through the development of Spreadsheet Model 2 and the data centre energy model, the application of previously published cable tunnel model outputs, and the analysis of the case studies, the research demonstrated that heat recovery from data centres offers significant opportunities for integration with urban heat networks, particularly in densely populated areas. Cable tunnels, while a smaller-scale source, were found to provide dual benefits of heat recovery and improved energy efficiency of electrical transmission systems. The findings demonstrate the technical feasibility and potential scalability of both approaches and provide evidence to support stakeholders and policymakers considering the integration of waste heat recovery into urban energy infrastructure.
Data centres are typically purpose-built or converted buildings, dedicated to the housing of computer servers, storage and networking equipment, which are responsible for day-to-day support of global computing needs. Data centres require careful design and management to ensure minimal downtime, security, and efficiency. While operating, large quantities of heat are generated by the IT equipment and need to be removed. According to published information, nearly 12,000 data centres are located in the United Kingdom alone. In addition, a substantial proportion of them are located in cities, close to potential heat users. Both of the above industrial processes i.e. cable tunnels and data centres operate continuously (24 hours a day) throughout the year, and a consequence of their normal operation is the conversion of electrical energy to low-temperature heat, which is typically rejected to the atmosphere. This thesis presents the results of a research study that investigated the potential for recovery of waste heat from cable tunnels and data centres. It quantified and analysed the benefits, including reductions in carbon emissions and operational costs, and identified technical, economic and institutional barriers currently preventing heat recovery from these sources in the United Kingdom. For the cable tunnel case study, the analysis indicated potential annual savings of approximately 4,000 kWh of combined heat and electrical energy, 570 kilograms of CO₂e and £127 per metre of tunnel. Extrapolated across London’s existing 62.7 km cable tunnel network, this corresponded to potential annual savings of approximately 250.8 GWh of energy, 35,739 tonnes of CO₂e and £7.97 million. For the data centre case study, the best-performing heat recovery configuration, combining direct-to-chip liquid cooling with recovery from the data centre air and connection to a 4G heat network, reduced energy input and operational carbon emissions by approximately 86%, and operating costs by approximately 66%, relative to the gas boiler counterfactual. Through the development of Spreadsheet Model 2 and the data centre energy model, the application of previously published cable tunnel model outputs, and the analysis of the case studies, the research demonstrated that heat recovery from data centres offers significant opportunities for integration with urban heat networks, particularly in densely populated areas. Cable tunnels, while a smaller-scale source, were found to provide dual benefits of heat recovery and improved energy efficiency of electrical transmission systems. The findings demonstrate the technical feasibility and potential scalability of both approaches and provide evidence to support stakeholders and policymakers considering the integration of waste heat recovery into urban energy infrastructure.
| Original language | English |
|---|---|
| Qualification | Doctor of Philosophy |
| Awarding Institution |
|
| Supervisors/Advisors |
|
| Award date | 26 Sept 2026 |
| Publisher | |
| DOIs | |
| Publication status | Published - 26 Sept 2026 |
UN SDGs
This output contributes to the following UN Sustainable Development Goals (SDGs)
-
SDG 7 Affordable and Clean Energy
-
SDG 11 Sustainable Cities and Communities
Cite this
- APA
- Author
- BIBTEX
- Harvard
- Standard
- RIS
- Vancouver